Today, I have been updated with news from OC Transpo having received a submission from Rideau Transit Group (RTG), which in their opinion have reached substantial completion on the Stage-1 Light Rail Transit (LRT) project.
The current status of the LRT project is that the train will undergo 12 days of rigorous testing by an independent certifier to ensure any deficiencies are corrected by the transit consortium.
The purpose of the testing will be to address :
- Safety
- Operational testing (Travel times for peak and off-peak period)
- Maintenance activities
- Vehicle performance
- Customer care systems testing
During this testing period trains will possibly not be moving on tracks, however testing is being done on other portions of the project. Upon completion of the testing period, if successful, RTG will handover the project to the City of Ottawa to continue testing procedures as part of its agreement to reach Revenue service availability.