Stage 2 LRT Project Update

July 8, 2019 to July 21, 2019 Overall Preparatory activities (borehole drilling, silt fence installation, site office mobilization, preconstruction surveys, etc.) are currently underway on each O-Train extension to facilitate the commencement of Stage 2 construction activities in 2019. O-Train Trillium Line South Extension Uplands Structures Yard set up Installation of fencing is now complete.…

Update on LRT Stage 1

Based on news received at this morning’s Finance and Economic Development Committee (FEDCO), I am cautiously optimistic that the LRT Stage 1 will be ready for transfer to the City of Ottawa in early August. I will continue to take RTG to task and hold them accountable for their performance and delivery on this project.…

Stage 2 LRT Project Update

June 24, 2019 to July 7, 2019 Overall: Preparatory activities (borehole drilling, silt fence installation, site office mobilization, pre-construction surveys, etc.) are currently underway on each O-Train extension to facilitate the commencement of Stage 2 construction activities in 2019. O-Train Trillium Line South Extension Uplands Structures Yard set up Spreading of gravel, temporary road construction,…