Update on LRT Stage 2

Stage 2 preparatory work continues along the East Extension corridor, at Ottawa Road 174. Kiewit-Eurovia-Vinci has completed significant geotechnical investigations via borehole drilling. They continue to remove some trees and vegetation (only what is required for construction) on both the north and south sides of Highway 174. They have begun the slight relocation of highway…

Transit Commission Update

Today at Transit Commission, an update was provided on how OC Transpo plans to address the service reliability issues with the train and the bus service across the City. This includes the following items: $2 million to provide for increased Para Transpo service; Provide new and improved connections to Line 1 –new growth areas, earlier/later…