Stage 2 LRT update

Overall Preparatory activities (borehole drilling, top soil stripping, site office mobilization, pre-construction surveys, tree clearing, etc.) are currently underway on each O-Train extension. O-Train Trillium Line South Extension Walkley Maintenance and Storage Facility (MSF) – In coordination with OC Transpo Rail Operations, preparatory works such as surveying, clean up, trackwork and fencing are underway at…

LRT Stage 2 update

O-Train Trillium Line South Extension Walkley Maintenance and Storage Facility (MSF) In coordination with OC Transpo Rail Operations, preparatory works such as surveying, clean up, trackwork and fencing are underway at the future site of the new Walkley Yard Maintenance and Storage Facility. Tree clearing will take place in early September within the footprint of…

Stage 2 LRT Project Update

July 22, 2019 to August 4, 2019 Overall Preparatory activities (borehole drilling, top soil stripping, site office mobilization, preconstruction surveys, etc.) are currently underway on each O-Train extension to facilitate the commencement of Stage 2 construction activities in 2019. O-Train Trillium Line South Extension Borehole drilling between Greenboro Station and Bayview Station  Borehole drilling is…

LRT Stage 1 Update

Today, I have been updated with news from OC Transpo having received a submission from Rideau Transit Group (RTG), which in their opinion have reached substantial completion on the Stage-1 Light Rail Transit (LRT) project. The current status of the LRT project is that the train will undergo 12 days of rigorous testing by an…

Stage 2 LRT Project Update

July 8, 2019 to July 21, 2019 Overall Preparatory activities (borehole drilling, silt fence installation, site office mobilization, preconstruction surveys, etc.) are currently underway on each O-Train extension to facilitate the commencement of Stage 2 construction activities in 2019. O-Train Trillium Line South Extension Uplands Structures Yard set up Installation of fencing is now complete.…

Update on LRT Stage 1

Based on news received at this morning’s Finance and Economic Development Committee (FEDCO), I am cautiously optimistic that the LRT Stage 1 will be ready for transfer to the City of Ottawa in early August. I will continue to take RTG to task and hold them accountable for their performance and delivery on this project.…

Stage 2 LRT Project Update

June 24, 2019 to July 7, 2019 Overall: Preparatory activities (borehole drilling, silt fence installation, site office mobilization, pre-construction surveys, etc.) are currently underway on each O-Train extension to facilitate the commencement of Stage 2 construction activities in 2019. O-Train Trillium Line South Extension Uplands Structures Yard set up Spreading of gravel, temporary road construction,…