Stage 2 LRT Project Update

July 22, 2019 to August 4, 2019 Overall Preparatory activities (borehole drilling, top soil stripping, site office mobilization, preconstruction surveys, etc.) are currently underway on each O-Train extension to facilitate the commencement of Stage 2 construction activities in 2019. O-Train Trillium Line South Extension Borehole drilling between Greenboro Station and Bayview Station  Borehole drilling is…

Federal government adds $1 Million to planned arena renovation

Today, the federal government announced it was joining the City of Ottawa and providing $1 million towards the renovation and expansion of the Blackburn Arena. This renovation is a key infrastructure renewal project for the City, one that invests in the local community to make the arena a more inclusive and functional space. With the…

LRT Stage 1 Update

Today, I have been updated with news from OC Transpo having received a submission from Rideau Transit Group (RTG), which in their opinion have reached substantial completion on the Stage-1 Light Rail Transit (LRT) project. The current status of the LRT project is that the train will undergo 12 days of rigorous testing by an…

Ward Office Hours

Please note that during the summer months, my team and I are out and about in Innes Ward local parks and the community. My ward office will therefore be staffed intermittently. If you would like to meet, please set up an appointment by emailing Laura.Dudas@ottawa.ca or calling 613-580-2472.

Stage 2 LRT Project Update

July 8, 2019 to July 21, 2019 Overall Preparatory activities (borehole drilling, silt fence installation, site office mobilization, preconstruction surveys, etc.) are currently underway on each O-Train extension to facilitate the commencement of Stage 2 construction activities in 2019. O-Train Trillium Line South Extension Uplands Structures Yard set up Installation of fencing is now complete.…